SOLAR PRODUCTION OF INDUSTRIAL PROCESS STEAM, FINAL TECHNICAL REPORT FOR THE PERIOD SEPTEMBER 26, 1977 THROUGH JUNE 26, 1978

by ACUREX CORPORATION,

Technical Report, 1978

Barcode

CSP Unique ID 190682185

Status

Electronic Resource

Call number

**Click on MARC view for more information on this report.**

Publication

1347; Report; November 1978.

Language

Library's review

ABSTRACT:
The technical and economic feasibility of generating low pressure steam, 446K, 862 kPa (345°F, 125 psia) for an industrial process is being demonstrated at the Johnson & Johnson plant in Sherman, Texas. This report summarizes the work completed during Phase I (Analysis and Design); Phase
Show More
II (Fabrication and Installation) is currently in progress and should be completed in early 1979; Phase III (Operation and performance Evaluation) will begin at the conclusion of Phase II.
Show Less