ABSTRACT:
Under Cooperative Agreement DE-FC03-79CS30310. the U.S. Department of Energy, the Columbia Gas System Service Corporation and the USS Chemicals Division of United States Steel Corporation are jointly funding a project to design a 50.400 square foot solar energy system to provide 150 psi
Under Cooperative Agreement DE-FC03-79CS30310. the U.S. Department of Energy, the Columbia Gas System Service Corporation and the USS Chemicals Division of United States Steel Corporation are jointly funding a project to design a 50.400 square foot solar energy system to provide 150 psi
Show More
industrial process steam for the production of polystyrene at the USS Chemicals Haverhill, Ohio plant. The design phase of the project (Phase I) was originally scheduled for the eight-month period from September 28, 1979 through May 31, 1980. It is expected that the agreement period will be formally extended until July 31, 1980. This report covers the period January 1, 1980 through May 31, 1980. Show Less