10-MWE SOLAR PILOT PLANT HELIOSTAT INSTALLATION INSTRUCTIONS

by U.S. DEPARTMENT OF ENERGY/MARTIN MARIETTA CORPORATION,

Technical Report, 1979

Barcode

CSP Unique ID 190682800

Status

Electronic Resource

Call number

**Click on MARC view for more information on this report.**

Publication

DOE ET 21007 7; Report; January 1979.

Language

Library's review

ABSTRACT:
This installation plan includes the steps and tooling necessary for installation of a heliostat assembly in the heliostat field. The sequence of the steps will be followed as planned. Exceptions to the sequence shall be negotiated between the installation supervisor, site installation
Show More
manager, safety/quality representative and SFDI representative. When negotiating exceptions, considerations shall be given to the following items:
a. Access to heliostat foundation
b. Pointing/ bias schedule and progress
c. Installation schedule impact
d. Sub-assembly(s) availability
e. Availability and utilization of installation tools and service equipment.
Show Less