ABSTRACT:
OBJECTIVES - 1.1 Demonstrate proper voltage and phase rotation at all distribution panels. 1.2 Demonstrate proper voltage at each heliostat power plug. 1.3 Demonstrate acceptable transformer oil tests before and after energizing. 1.4 Demonstrate acceptable transformer temperatures after
Show More
energizing. 1.5 Measure satisfactory voltages at heliostats during field stow operation.