THERMAL STORAGE SYSTEM, PREOPERATIONAL TEST, PROCEDURE 205/250, 10 MWE SOLAR PILOT PLANT, DAGGETT, CALIFORNIA

by U.S. DEPARTMENT OF ENERGY/SOUTHERN CALIFORNIA EDISON COMPANY,

Technical Report, 1981

Barcode

CSP Unique ID 190682997

Status

Electronic Resource

Call number

**Click on MARC view for more information on this report.**

Publication

DOE SF 10499 T64; Report; July 1981.

Language

Library's review

ABSTRACT:
This procedure addresses checkout and operation of TSS Instrumentation, Controls, Red Line Unit logic, Interlock Logic System logic, and Valve and Pump Operations. The Appendices to this procedure have End to End Checkouts of system transducers and components. The appendices are
Show More
prerequisite tests to be accomplished prior to preoperational checks. Merely confirming that the prerequisite test has been accomplished satisfies many preoperational test requirements.