ABSTRACT:
This report was prepared for the Department of Energy under Contract No. DE-AC03-79SF10736. It presents the results of a ten (10) month study to develop a site specific conceptual design of a solar retrofit system for the ARCO Oil and Gas Company North Coles Levee Natural Gas Processing
The guidance and support of the Department of Energy Program Manager, Fred Corona, and the technical assistance and support of Jim Gibson of Sandia National Laboratories were of great benefit in the performance of this study and their contributions are hereby acknowledged.
The authors of the report are the persons responsible for performing the design and analysis work and include; F. A. Blake, A. J. Anderson, R. J. Thomas and R. L. Henry of Northrup, Inc. and H. E. Wold, W. S. Deinlein and Louis Hartmangruber of ARCO Oil and Gas Co.
The report is bound in two books. One is the technical report of the conceptual design effort and the other is an appendices which contains quantities of supporting data and methods too voluminous for inclusion in the technical report. Section 1 of the technical report, "Executive Summary" is also published under separate cover.
This report was prepared for the Department of Energy under Contract No. DE-AC03-79SF10736. It presents the results of a ten (10) month study to develop a site specific conceptual design of a solar retrofit system for the ARCO Oil and Gas Company North Coles Levee Natural Gas Processing
Show More
Plant near Bakersfield, California.The guidance and support of the Department of Energy Program Manager, Fred Corona, and the technical assistance and support of Jim Gibson of Sandia National Laboratories were of great benefit in the performance of this study and their contributions are hereby acknowledged.
The authors of the report are the persons responsible for performing the design and analysis work and include; F. A. Blake, A. J. Anderson, R. J. Thomas and R. L. Henry of Northrup, Inc. and H. E. Wold, W. S. Deinlein and Louis Hartmangruber of ARCO Oil and Gas Co.
The report is bound in two books. One is the technical report of the conceptual design effort and the other is an appendices which contains quantities of supporting data and methods too voluminous for inclusion in the technical report. Section 1 of the technical report, "Executive Summary" is also published under separate cover.
Show Less