ABSTRACT:
Volume 1 of this final report examines the programmatic, technical, and economic results of El Paso Electric Company's (EPE) Newman Unit 1 Solar Repowering Program. The Newman Unit 1 Solar Repowering Program was funded by DOE for the period of September 30, 1979 to July 15, 1980. The
Volume 1 of this final report examines the programmatic, technical, and economic results of El Paso Electric Company's (EPE) Newman Unit 1 Solar Repowering Program. The Newman Unit 1 Solar Repowering Program was funded by DOE for the period of September 30, 1979 to July 15, 1980. The
Show More
principal objective was to develop a conceptual design and cost estimate for solar repowering Newman Unit 1 that has the potential for construction and operation by 1985, makes use of available solar thermal technology, and provides the best economics for this application. Show Less