Reliability, Availability and Maintainability Audit of the T.H. Wharton Plant, Units 3 and 4, Houston Lighting and Power

by Arinc Research Corporation,

Other authorsR. C. Young
Technical Report, 1984

Barcode

CSP Unique ID 190683241

Status

Electronic Resource

Call number

**Click on MARC view for more information on this report.**

Publication

EPRI AP 3495; Report; May 1984.

Language

Library's review

ABSTRACT:
This report presents the results of an on-site reliability, availability, and maintainability (RAM) audit of the Houston Lighting and Power T. H. Wharton Plant, Units 3 and 4. Outage reports from January 1978 through October 1982 were analyzed. Overhaul activities on three combustion
Show More
turbines were observed, and plant personnel were informally interviewed.

The objectives of the audit were as follows:
• Observe overhaul activities to identify RAM characteristics of plant equipments, including service lives
• Review plant records to determine root causes of unavailability
• Investigate relationships between operation/maintenance practices and RAM characteristics

The project established a framework for performance of RAM audits.