EPRI AP 5276; Report; June 1987.
Language
Library's review
ABSTRACT:
The Electric Power Research Institute (EPRI) contracted with ARINC Research Corporation to perform availability assessments of an integrated coal gasification-combined-cycle (IGCC) design. The objective of the study was to quantify the availability impact associated with several design and
The Electric Power Research Institute (EPRI) contracted with ARINC Research Corporation to perform availability assessments of an integrated coal gasification-combined-cycle (IGCC) design. The objective of the study was to quantify the availability impact associated with several design and
Show More
operating options specified by EPRI. In addition, several scheduled maintenance options for the IGCC plant were evaluated. Show Less