10 MWE Solar Thermal Central Receiver Pilot Plant mid-term test and evaluation review : July 20-21, 1983

by Livermore Sandia National Laboratories, CA

Technical Report, 1984

Barcode

CSP Unique ID 190706825

Status

Electronic Resource

Call number

**Click on MARC view for more information on this report.**

Publication

SAND Report: SAND83-8038, January 1984.

Language

Library's review

ABSTRACT:
A Mid-Term Review of the Barstow pilot plant was held in Barstow, California, in July 1983. At that meeting, a panel of representatives from various utilities and repowering studies gathered to review the first year of the Test and Evaluation Phase, as well as the planned activities for
Show More
the second year of that phase. The panel concurred that plant checkout and testing have progressed well, and they fully support next year's test plan. The panel's comments and suggestions for the last year of testing are included in this report.