This report describes the work done by General Atomic Company to design, fabricate, install, and startup the Fixed Mirror Solar Concentrator (FMSC) at Sandia Laboratories for the Department of Energy. Total system cost was $773 per m2. The system cost projection for a commercial plant is
This report describes the work done by General Atomic Company to design, fabricate, install, and startup the Fixed Mirror Solar Concentrator (FMSC) at Sandia Laboratories for the Department of Energy. Total system cost was $773 per m2. The system cost projection for a commercial plant is
Show More
$188.73 per m2. At design conditions, with the oil inlet temperature at 245°C and the oil outlet temperature at 316°C, the peak system efficiency at noon was 36.8%. Show Less