Link to document:
Status
Electronic Resource
Call number
Publication
SAND Report: SAND77-8510, September 1977.
Collection
Language
Library's review
ABSTRACT:
The first solar central receiver pilot plant will be built in Barstow, California, starting in 1978. Experimental versions of competing subsystem designs have been constructed and tested. Sandia Laboratories is valuating the technology that resulted from these experiments in order to
The first solar central receiver pilot plant will be built in Barstow, California, starting in 1978. Experimental versions of competing subsystem designs have been constructed and tested. Sandia Laboratories is valuating the technology that resulted from these experiments in order to
Show More
develop a recommendation for the conceptual design for this pilot plant. Show Less