50 kW Solar Concentrators with Stirling Engine, Results of the Six Months of Operation in Saudi Arabia

by A. Al-Rubaian,

Technical Report

Barcode

CSP Unique ID 3039

Status

Electronic Resource

Publication

Publisher Unknown

Language

Library's review

ABSTRACT:
This paper describes the results of the first 900 hours of operation by the two 50 kW Dish with Stirling engine units in Riyadh, Saudi Arabia. The units were constructed, installed and are being operated as a joint project between the Federal Ministry for Research and Technology (BMFT) for
Show More
West Germany and King Abdulaziz City for Science and Technology (KACST) for Saudi Arabia. The Design and construction was led by Schlaich and Partner, Stuttgart who developed the novel 17m diameter membrane concentrator and who were responsible for the system design and integration incorporating a control system by MBB, and the 50 kW Stirling engine generator units by USAB of Malmo, Sweden. Construction ended in spring 1986 and a program of operation and evaluation was begun under the leadership of KACST with participation by DFVLR and Schlaich and Partner.
Show Less